Project Description

Client:   Fort Reno Water Plant
Location:   Tenleytown D.C.
Surface Area: 8,000 ft2
Year Completed:   2015
Project Manager: Bill
Comfort Specialist: Brendan

fort_reno_from_dcwater-dish

The Challenge

To be able to prevent outside air from reaching the 5.4 million gallon reservoir below the vent houses and to take samples of the water.

The Solution

We installed an air curtain inside the door way to cut off the air flow; We also installed piping and pumps into the reservoir to take samples of the water. This required our technicians to undergo confined space training and specialized materials training for working inside the reservoir.